- W6802/2023/1
-
Decision
Amendment Report - Granted 27 November 2024
- Type Works approval
- Holder FMG Solomon Pty Ltd
- Premises name Solomon Mine
- Location details Mining tenements E47/1011, E47/1334, E47/1532, M47/1409, M47/1410, M47/1411, M47/1413, M47/1431, M47/1453, M47/1466, M47/1473, M47/1474, M47/1475, L47/293, L47/294, L47/296, L47/301, L47/351, L47/360, L47/362, L47/363, L47/367, L47/381, E47/382, L47/391, L47/392, L47/397, L47/471, L47/472, L47/710, L47/711, L47/813, L47/814, P47/1279, P47/1286, P47/1287, P47/1304, P417/1305, P47/1735, P47/1736 and portion of E47/1319, E47/1333, E47/1398, E47/1399, E47/1447, E47/3094, E47/3464, L47/361 and L47/713 as defined by the coordinates in Schedule 2
- Suburb MT SHEILA WA 6751
- Local Government Ashburton Shire
- Date issued 2023-07-31
- Date commenced 2023-07-31
- Date of expiry 2028-07-30
-
Category
5 - Processing or beneficiation of metallic or non‑metallic ore
64 - Class II or III putrescible landfill site
77 - Concrete batching or cement products manufacturing
- Comment Appeal period commences 28 November 2024