- L7851/2002/6
-
Decision
Amendment Report - granted 17 August 2020
Amendment Report - granted 12 March 2021
Amendment Report - granted 18 November 2021
Amendment Report - granted 22 April 2022
Amendment Report - granted 25 November 2022
Amendment Report - granted 22 January 2024
Amendment Report - granted 12 December 2024
Amendment Report - granted 01 May 2026
-
Amendment Notice
Amendment Notice 1 - 06 October 2017
- Type Licence
- Holder BHP Iron Ore Pty Ltd
- Premises name Mining Area C Project
- Location details Mining Tenement ML281SA, ML249SA and Exploration Lease E47/1540-I
- Suburb NEWMAN WA 6753
- Local Government East Pilbara Shire
- Date issued 13-11-2014
- Date commenced 17-11-2014
- Date of expiry 16-11-2027
-
Category
5 - Processing or beneficiation of metallic or non‑metallic ore
6 - Mine dewatering
12 - Screening of material
52 - Electric power generation
54 - Sewage facility
63 - Class I inert landfill site
73 - Bulk storage of chemicals etc.
85B - Water desalination plant
89 - Putrescible landfill site
- Comment Appeal period commences 04 May 2026
-
Annual Audit Compliance Reports