Licences and works approvals
L6079/1988/13
Decision |
Amendment Report - granted 07 June 2022 Amendment Report - granted 02 October 2024 Decision Report - granted 08 May 2025 |
Amendment Notice |
|
Type | Licence |
Holder | Greatland Pty Ltd |
Premises name | Telfer Gold Mine |
Location details | Mining Leases: G45/1, G45/2, G45/3, G45/4, L45/99, L45/106, L45/110, L45/622, M45/6, M45/7, M45/8, M45/9, M45/10, M45/11, M45/33, M45/203, M45/204, M45/205, M45/206, M45/207, M45/208, M45/209, M45/210, M45/211, M45/249, M45/631, M45/632, M45/633, M45/709, M45/710, M45/720, M45/721, M45/722 and M45/772 |
Suburb | TELFER WA 6762 |
Local Government | East Pilbara Shire |
Date issued | 2015-10-08 |
Date commenced | 2015-10-12 |
Date of expiry | 2034-10-11 |
Category |
5 - Processing or beneficiation of metallic or non‑metallic ore 6 - Mine dewatering 7 - Vat or in situ leaching of metal 12 - Screening of material 52 - Electric power generation 54 - Sewage facility 57 - Used tyre storage (general) 63 - Class I inert landfill site 64 - Class II or III putrescible landfill site 73 - Bulk storage of chemicals etc. |
Annual Audit Compliance Reports |
|
L9376/2023/1
Decision |
Decision Report - Granted 17 July 2023 Amendment Report - Granted 02 October 2024 |
Type | Licence |
Holder | Onslow Infraco Pty Ltd |
Premises name | Ashburton Infrastructure Project – Haul Road |
Location details | Within mining tenements L08/202, L08/205, L08/206, L08/210, L08/211, L08/212, L08/214, L08/215, L08/216, L08/219, L08/231, L08/232, L08/253 and L08/199 |
Suburb | ONSLOW WA 6710 |
Local Government | Ashburton Shire |
Date issued | 2023-07-17 |
Date commenced | 2023-07-17 |
Date of expiry | 2028-07-16 |
Category |
12 - Screening of material 54 - Sewage facility |
Annual Audit Compliance Reports |
|
W6772/2023/1
Decision |
Amendment Report - granted 01 October 2024 |
Type | Works approval |
Holder | Chevron Australia Pty Ltd |
Premises name | Gorgon LNG Project |
Location details | Part of Crown Lease L077431, Certificate of Title Volume LR3168 Folio 315, Site 1 on Deposited Plan 409277; Part of Crown Lease L077428, Certificate of Title LR3158 Folio 476, Site 5 on Deposited Plan 64220; Temporary Wastewater Injection Facilities Licence LIC00554/2009_1_43; Part of Revised Service Corridor Easement L641372, Certificate of Title Volume LR3142 Folio 58, Deposited Plan 91514 and; Onshore Feed Gas Pipeline Right of Way Easement L466759, Certificate of Title Volume LR3142 Folio 58, Deposited Plan 91514. As defined in Figure 1 of Schedule 1 |
Suburb | BARROW ISLAND WA 6712 |
Local Government | Ashburton Shire |
Date issued | 2023-08-17 |
Date commenced | 2023-08-17 |
Date of expiry | 2029-08-16 |
Category |
12 - Screening of material 54 - Sewage facility 61 - Liquid waste facility |
W6915/2024/1
Decision | Decision Report - granted 30 September 2024 |
Type | Works approval |
Holder | CSBP Limited |
Premises name | CSBP Kwinana |
Location details | Part of Lot 20 on Diagram 78086, Volume 1918 / Folio 244 and Part of Lot 18 on Plan 17311, Volume 2058 / Folio 310 |
Suburb | KWINANA WA 6167 |
Local Government | Kwinana City |
Date issued | 2024-09-30 |
Date commenced | 2024-09-30 |
Date of expiry | 2028-09-29 |
Category |
31 - Chemical manufacturing 75 - Chemical blending or mixing not causing discharge |
W6932/2024/1
Decision | Decision Report - granted 26 September 2024 |
Type | Works approval |
Holder | Rhodes Ridge Management Services Pty Ltd |
Premises name | Rhodes Ridge |
Location details | Part of Mining Tenement TR 70/4882 |
Suburb | NEWMAN WA 6753 |
Local Government | East Pilbara Shire |
Date issued | 2024-09-26 |
Date commenced | 2024-09-27 |
Date of expiry | 2027-09-26 |
Category |
85 - Sewage facility |
L9267/2020/2
Decision | Decision Report - granted 26 September 2024 Previous Decision Report - 04 February 2021 |
Type | Licence |
Holder | Mario Michelle Giacci |
Premises name | Gwindinup Sand and Gravel Pits |
Location details | Lot 287 and Lot 393, 79 Lowrie Road South Western Highway |
Suburb | GWINDINUP WA 6237 |
Local Government | Capel Shire |
Date issued | 2024-09-26 |
Date commenced | 2024-09-26 |
Date of expiry | 2034-09-25 |
Category |
12 - Screening of material |
Annual Audit Compliance Reports |
L7438/2000/9
Decision | Amendment Report - granted 30 November 2023 Amendment Report - granted 26 September 2024 |
Amendment Notice |
Type | Licence |
Holder | Milne Agrigroup Pty Ltd |
Premises name | Milne Feeds |
Location details | 103-105 Welshpool Road |
Suburb | WELSHPOOL WA 6106 |
Local Government | Canning City |
Date issued | 2012-03-23 |
Date commenced | 2012-03-24 |
Date of expiry | 2030-03-23 |
Category |
23 - Animal feed manufacturing 61 - Liquid waste facility |
Annual Audit Compliance Reports | 01 November 2019 - 31 October 2020 01 November 2020 - 31 October 2021 |
W6555/2021/1
Decision | Decision Report - granted 06 June 2022 Amendment Report - granted 15 August 2022 Amendment Report - granted 26 September 2024 |
Type | Works approval |
Holder | Pilbara Iron Pty Ltd |
Premises name | Ti Tree Rail Camp Wastewater Treatment Plant |
Location details | Miscellaneous Licence L47/47 |
Suburb | TOM PRICE WA 6751 |
Local Government | Ashburton Shire |
Date issued | 2022-06-05 |
Date commenced | 2022-06-05 |
Date of expiry | 2027-06-06 |
Category |
85 - Sewage facility |
W6905/2024/1
Decision | Decision Report - granted 24 September 2024 |
Type | Works approval |
Holder | Van Tiep Doan, Thi Chinh Duong and Van Phu Doan |
Premises name | Mushroom Compost Facility |
Location details | Lots 800 and 801 Military Road |
Suburb | MUCKENBURRA WA 6503 |
Local Government | Gingin Shire |
Date issued | 2024-09-24 |
Date commenced | 2024-09-24 |
Date of expiry | 2027-09-23 |
Category |
67A - Compost manufacturing and soil blending |
L7183/1997/11
Decision |
Amendment Report - granted 04 February 2016 Amendment Report - granted 09 February 2024 Amendment Report - granted 25 September 2024 |
Type | Licence |
Holder | Dampier Salt Limited |
Premises name | Port Hedland Operations |
Location details | ML242SA, ML250SA, M269SA, AM70/00269, AML70/00242 and AML70/00250 |
Suburb | PORT HEDLAND WA 6721 |
Local Government | Port Hedland Town |
Date issued | 2013-09-12 |
Date commenced | 2013-09-22 |
Date of expiry | 2027-09-21 |
Category |
14 - Solar salt manufacturing |
Annual Audit Compliance Reports |
01 January 2020 - 31 December 2020 01 January 2021 - 31 December 2021 01 January 2022 - 31 December 2022 |
L8395/2009/2
Decision |
Amendment Report - granted 05 October 2022 Amendment Report - granted 24 September 2024 |
Amendment Notice |
|
Type | Licence |
Holder | Electricity Generation and Retail Corporation T/A Synergy |
Premises name | Pinjar Gas Turbine Power Station |
Location details | Perry Road, Lot 500 on Plan 59628 Certificate of Title Volume 3158 Folio 926 Crown Reserve 50389 |
Suburb | PINJAR WA 6065 |
Local Government | Wanneroo City |
Date issued | 2011-09-01 |
Date commenced | 2011-10-01 |
Date of expiry | 2029-09-30 |
Category |
52 - Electric power generation |
Annual Audit Compliance Reports |
|
W6939/2024/1
Decision | Decision Report - granted 20 September 2024 |
Type | Works approval |
Holder | Crimson Metals Pty Ltd |
Premises name | Mount Gibson Gold Project WWTP |
Location details | Mining tenements M59/772, G59/72, L59/53 |
Suburb | PAYNES FIND WA 6612 |
Local Government | Yalgoo Shire |
Date issued | 2024-09-20 |
Date commenced | 2024-09-20 |
Date of expiry | 2027-09-19 |
Category |
64 - Class II or III putrescible landfill site 85 - Sewage facility |
L9253/2020/3
Decision | Decision Report - granted 24 September 2024 Previous Decision Reports: 25 September 2020, 21 September 2022 |
Type | Licence |
Holder | Mardie Minerals Pty Ltd |
Premises name | Mardie Trial Project |
Location details | Mining Tenement M08/526 |
Suburb | KARRATHA WA 6714 |
Local Government | Karratha City |
Date issued | 2024-09-24 |
Date commenced | 2024-09-25 |
Date of expiry | 2044-09-24 |
Category |
14 - Solar salt manufacturing |
L7333/1997/10
Decision |
Amendment Report - granted 28 October 2022 Amendment Report - granted 19 December 2022 Decision Report - granted 24 September 2024 |
Type | Licence |
Holder | Vasse Felix Pty Ltd |
Premises name | Vasse Felix Winery |
Location details | 71 Tom Cullity Drive, Being Lot 101 on Diagram 82806 |
Suburb | COWARAMUP WA 6284 |
Local Government | Augusta-Margaret River Shire |
Date issued | 2014-05-22 |
Date commenced | 2014-05-30 |
Date of expiry | 2035-05-29 |
Category |
25 - Alcoholic beverage manufacturing |
Annual Audit Compliance Reports |
|
L4706/1972/17
Decision |
Amendment Report - granted 01 July 2021 Amendment Report - granted 19 September 2024 |
Amendment Notice |
Amendment Notice 1 - 6 January 2017 |
Type | Licence |
Holder | Electricity Generation and Retail Corporation T/A Synergy |
Premises name | Muja Power Station |
Location details | Muja Power Station Road, Being Lot 5192 on Plan 213624, part Lot 4903 on Plan 167984, Lot 1 on Diagram 53100 and portion of State Forest 24 |
Suburb | COLLIE WA 6225 |
Local Government | Collie Shire |
Date issued | 2014-10-09 |
Date commenced | 2014-10-18 |
Date of expiry | 2036-10-17 |
Category |
12 - Screening of material 52 - Electric power generation 53 - Flyash disposal 61 - Liquid waste facility |
Annual Audit Compliance Reports |
|
L9116/2018/1
Decision |
Amendment Report - granted 19 September 2024 |
Type | Licence |
Holder | The Margaret River Dairy Company Pty Ltd |
Premises name | Margaret River Dairy |
Location details | 8063 Bussell Highway, Lot 108 on Deposited Plan 40314 Certificate of Title Volume 2549 Folio 790 |
Suburb | METRICUP WA 6280 |
Local Government | Busselton City |
Date issued | 2018-09-18 |
Date commenced | 2018-09-18 |
Date of expiry | 2038-09-17 |
Category |
17 - Milk processing |
Annual Audit Compliance Reports | 01 January 2020 - 31 December 2020 01 January 2021 - 31 December 2021 |
L9408/2023/1